We had a FANTASTIC weekend!!! We began our move-in officially on Monday when Ikea and Discount School Supplies each brought a truck load of supplies. Tuesday, December 22nd Two Men and a Truck moved all of the things from all SIX of our storage lockers over to one of the empty buildings at the school. It took them 12 hours to move all of our things. It was amazing.
On Tuesday night we bought and transported over 200 baskets to the school- that was a site to see for sure! On Thursday and Friday we emptied a very large bonus room and two garages into the school. On Saturday and Sunday we emptied three classrooms from the current Little School and thinned some of the surplus from what will be the half day classrooms, throwing away many very loved, and very tired items.
As of this evening, Sunday night, we are probably 85% done putting it all away. The classrooms are so beautiful and different. The teachers have brought their individual personalities and points of view to their classroom compositions. It is just incredible to see it all come together.
The remainder of the flooring was also installed over the weekend.
The week of December 28-December 31:
Monday: We will have all of our final inspections AND HAVE OUR WATER METER INSTALLED AND WATER TURNED ON!!! We will also have the first load of mulch installed. A total of 5 tractor trailer loads of mulch will be delivered and spread this week. The mulch is going to absolutely transform the campus.
Tuesday: Any remaining site inspections (if something has to be fixed in order for us to pass our final inspection) will be completed. We will be putting away all of the office, art room, and dining room furniture. We will also be making all of our last minute classroom changes prior to our North Carolina Division of Child Development licensing inspection on Wednesday morning. If all goes as planned we will have our temporary license on Wednesday! At worst case scenario we will have them return on Thursday the 31st.
We are hoping to rest on New Year's Day.
NEEDS: WE NEED TO ASK THAT PARENTS DO NOT VISIT THE SITE BEFORE 5:00 AS OSHA REGULATIONS FORBID VISITS DURING CONTRACTOR WORK HOURS. PLEASE DO NOT WANDER THE SITE ALONE. ANY VIOLATION COULD CAUSE OUR OPENING TO BE DELAYED.
We are really, really, REALLY excited now. We are beginning to imagine what it is going to be like to see the children arrive on the 4th. What an exciting time!
Please write Christa at christaniven@thelittleschool.net with any questions. No one will be answering the Little School phone this week. Thanks and we can't wait to see you soon.
REMINDER: Our ribbon cutting ceremony is scheduled from 3:00-4:00 on Sunday, January 3, 2010. Please be sure to join us for that exciting event.
Waterstone Campus Blog
This blog is designed to keep you informed weekly of the construction and development of the new Little School at the Waterstone Campus. We plan to update every Friday until construction is completed.
Showing posts with label Thank you. Show all posts
Showing posts with label Thank you. Show all posts
Sunday, December 27, 2009
Thursday, December 24, 2009
Too Many People to Thank in One Blog!
As of this evening we have our conditional certificate of occupancy and we are ready to begin to move into the buildings!!!
Yay! Hurray!! Yippee!!!
We have accomplished the following:
1. Fencing is complete- and SO cute
2. Heating in all three of our buildings
3. Electricity in all three of our buildings
4. The site is just about completely graded and expectantly awaiting mulch next week- Mulch is going to bring about a MIRACULOUS transformation!!!
5. The concrete and walkways are in
To Be Completed Next Week:
1. We are awaiting our water meter so that we can run water. This is a big one. We need lots of prayer and well-wishes going into the weekend.
2. Mulch
3. The remainder of the flooring
4. Permanent certificate of occupancy
We want to say a great big thank you to Kenny Keel and our very own (and much beloved) Eric Peterson without whom the water meter would be impossible. We also need to say thank you to the entire office of inspections and zoning department, but especially to Michael Rettie who has been just amazing to work with this week. Our poor exhausted team of subcontractors, general contractors, site superintendents and project manager and husbands, parents, staff and children are so incredibly dedicated and determined to get us ready for the 4th. We just don't have room to sing their praises adequately so instead we will just say a profound THANK YOU TO YOU ALL- You know who you are and so do we!
We hope that you all have a wonderful and joyous holiday. We can't wait to see you all soon.
Jennifer, Wendy and Christa
Yay! Hurray!! Yippee!!!
We have accomplished the following:
1. Fencing is complete- and SO cute
2. Heating in all three of our buildings
3. Electricity in all three of our buildings
4. The site is just about completely graded and expectantly awaiting mulch next week- Mulch is going to bring about a MIRACULOUS transformation!!!
5. The concrete and walkways are in
To Be Completed Next Week:
1. We are awaiting our water meter so that we can run water. This is a big one. We need lots of prayer and well-wishes going into the weekend.
2. Mulch
3. The remainder of the flooring
4. Permanent certificate of occupancy
We want to say a great big thank you to Kenny Keel and our very own (and much beloved) Eric Peterson without whom the water meter would be impossible. We also need to say thank you to the entire office of inspections and zoning department, but especially to Michael Rettie who has been just amazing to work with this week. Our poor exhausted team of subcontractors, general contractors, site superintendents and project manager and husbands, parents, staff and children are so incredibly dedicated and determined to get us ready for the 4th. We just don't have room to sing their praises adequately so instead we will just say a profound THANK YOU TO YOU ALL- You know who you are and so do we!
We hope that you all have a wonderful and joyous holiday. We can't wait to see you all soon.
Jennifer, Wendy and Christa